20170619_125131

 

Scripps Coastal Clinic at Plaza 76 in Oceanside
Started 03/2017 and Completed 06/2017
Contractor: Current Solar Contracting

 

 

 

Roughly 1100 Panels installed between the Roof and 3 New Carport Structures in the Parking Lot, about 270 KW.
site_Map_layout_Plaza76

Panels installed on the existing TPO Roof of the Clinic installed with “Zero Penetration” brackets that withstand wind speeds up to 110mph.
Plaza 76 Panel Layout

Planning for this project started in December 2016 and since this building is occupied and in full operation Monday – Friday, we knew this was going to be tricky. Once we received our Stamped City Permit and Notice to Proceed (NTP) we began immediately.

BEFORE PICTURES:

20161206_090437_resized_120161206_090457_resized20161206_090511_resized20161206_090819_resized20161206_090846_resized20161206_090853_resized20161206_090916_resized20161206_090432_resized_1

DURING – PROGRESS PICTURES:

20170517_134357_resized20170519_095042_resized20170519_101109_resized

Quite a few trees in islands had to be removed and the parking lot needed to be re-paved as it was already in need anyway and we had to relocate our ADA Spots as well.

Here are the AFTER PICTURES from the roof:
20170512_102204_resized20170512_102208_resized20170512_102252_resized20170512_102318_resized20170512_102424_resized20170512_102431_resized

AFTER IMAGES – New Steel Carports in Parking Lot with Panels on Top and Inverters on Columns and LED Lighting Underneath:
20170601_110342_resized20170603_060254_resizedLot After1Lot After3